Creating records manually
Enter an RFI, a submittal or a change order that reached you outside email or Procore, so it is tracked and answered like any other.
Not every RFI arrives by email. A contractor asks a question on a call, hands over a printed submittal, or raises a change in a site meeting. You can enter these records yourself so they sit in the same log, with the same thread, as the ones Cogram files for you.
Creating a record
Open the RFIs, Submittals or Change orders page under Contract admin.
Click Create at the right of the toolbar.
Choose the Project. When the page is scoped to a project, it is chosen for you.
Check the Number. Cogram suggests the next number in the project's log, for example
RFI-015afterRFI-014. You can change it. If the number is already used in the project, Cogram tells you, and you can still create the record.Enter the Subject (RFIs) or Title (submittals and change orders).
In From, pick the contractor contact who sent it, or type their email address to add them as a new contact.
Add the question or description, and attach the files they sent. Drop files or folders, choose them, or click Add from project to attach documents already in the project.
Open the details to set the rest:
RFIs: assignee, due date, spec section and drawing.
Submittals: assignee, due date, spec section, drawing and package.
Change orders: cost impact and currency, schedule impact in days, date received and response due date. The type (PCO, CO or CCD) sits next to the number.
Click Create RFI, Create submittal or Create change order. Cogram opens the new record.
An RFI or submittal is received today unless you set Date received. Leave Due date empty and Cogram sets it from the project's review period. See Received and due dates.
What Cogram does with it
The record is filed as received from the contact you chose. Its thread starts with their question or description and the files they sent, as if it had arrived by email. Everything works as it does for a record filed from email: you can reply, run a review, draft a response, forward it to a consultant, and assign it. Your response is emailed to the contact. The record's Source reads Added manually.
A new record is assigned to you unless you pick someone else in Assignee. A record that Cogram files from email is assigned to the person whose mailbox it came in through. You can reassign or unassign either one on the record.
Automations that start when an RFI or submittal is created run for these records too. In an automation's trigger, the source filter calls them Manual.
Projects connected to Procore
When a project syncs RFIs and submittals from Procore, Procore stays the source of truth for them. You can't create an RFI or a submittal in Cogram on that project: the project is grayed out in the picker, and the Create button is disabled while the page is scoped to it. Create the record in Procore and it syncs to Cogram.
Change orders don't sync with Procore, so you can create them on any project.
Who can create records
You need an RFI / Submittals seat (see Licensing), which also covers change orders, and you need to be an owner or member of the project. Project viewers can read records but can't create them.