Received and due dates
How Cogram sets the received date and the due date of an RFI or submittal, and how to change them.
Every RFI and submittal in Cogram has a received date and a due date. Cogram sets both when the record arrives, and you can change them on the record.
Received date
A record filed from email is received on the day the email was sent.
A record you create by hand is received on the day you create it, unless you set Date received in the create form.
To change it, open the record and pick a new Date received in the sidebar.
Due date
When a record arrives without a due date, Cogram sets one from the project's review period: the received date plus the number of days in the period. When the email states a date ("Response required by October 30", or "by Friday" read from the day the email was sent), Cogram uses that date instead.
To change the due date, open the record and pick a new Due date in the sidebar. Clear it to remove the due date. A due date can't be before the received date.
If you change the received date and the due date still follows the review period, the due date moves with it. A due date that someone chose stays as it is.
RFIs and submittals synced from Procore take both dates from Procore. Change them in Procore.
Review periods
Each project has a review period for RFIs and one for submittals, counted in calendar days. A new project starts at 10 days for RFIs and 14 days for submittals.
Open the project and go to Overview > Settings.
Under Review periods, enter the days your contract gives you for each.
Click Save.
A new period applies to records received after you save it. Existing due dates do not change.
Project owners can change the review periods.
Overdue records
A due date that has passed shows in red in the RFI and submittal lists and on their boards until the record is answered.